Projected to double Klabin’s production capacity in three years, the Puma Unit, the product of the Puma I Project, entailed total investments of R$8.5 billion for construction of the mill, which was inaugurated in 2016 and recognized as Paraná’s largest private project at that time.

Mill self-sufficient in power
generation

 
270
MW
in generation capacity

120 MW used by Klabin
150 MW supplied to Brazil’s power grid
Energy sufficient to supply a city of 500,000 inhabitants.

Área total construída

200

hectares
equivalent to 200 football fields

Competitiveness and efficiency

Average distance between forest and mill of approximately

100
km

Benchmark in forest stewardship

107,000
 hectares

of planted forests will supply the new mill

700

million
in taxes paid during the investment phase

300

million
in annual taxes generated by mill operations

A
23,5 km

railway line connects the Puma Unit to the Central do Paraná railway network, passing through the cities of Ponta Grossa and Curitiba. The logistics structure also includes a new highway to connect the company’s reforestation areas and the Monte Alegre Unit in Telêmaco Borba to the Puma Unit.